| Key Concept and
Formulas for PMP Exam |
| Earn Value Formulas |
Project
Selection Financials |
PV (Planned Value)
= BCWS (Budgeted Cost of Work Scheduled
EV
(Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC
(Actual Cost) = ACWP (Actual Cost of Work Performed)
SV
= EV – PV (minus is behind schedule)
CV
= EV – AC (minus is over budget)
SPI
= EV/PV (Less than 1 is behind schedule)
CPI
= EV/AC (Less than 1 is over budget)
EAC
= AC + (BAC-EV) Use
when variances are atypical
EAC
= AC + [(BAC-EV)/CPI] Use
when variances are typical
(Note:
This is the same as EAC = BAC/CPI)
VAC
= BAC – EAC
ETC
= BAC – EV Use when
variances are atypical
ETC
= (BAC – EV)/CPI Use when
variances are typical
ETC
= EAC – AC Use when
original estimates were flawed
|
NPV
(Net Present Value) = FV/(1+r)n
FV=
Future Value, r= interest rate, n= no. of time periods
Higher
NPV is better
IRR
(Internal Rate of Return) = Solve the NPV equation for “r”
Also
called Hurdle Rate
Higher
IRR percentage is better
BCR
(Benefit/Cost Ratio)
Higher
BCR is better.
Beware,
exam can call it CBR, where lower is better
ROI
(Return on Investment) = Earnings/Investment
Higher
ROI is better
Payback
Period = Time to recover cost of the project
Lower
payback period is better
Cash
Flow = Cash In – Cash Out
|
| Network Diagram |
Calculating Stackor Float |
Precedence
Diagramming Method (PDM)
-
Also
called Activity on Node (AON): Activities are in boxes
-
Most
commonly used today
-
Has
4 relationships: F-S, S-S, F-F, S-F
-
No
“dummies” (zero duration dependencies) allowed
-
Can
analyze using either Three-Point Estimates or CPM
Arrow
Diagramming Method (ADM)
Graphical
Evaluation and Review Technique (GERT)
|
Total Float (also called Slack,
Float, or Project Float) is the total amount of time an activity can be delayed
without delaying the project finish date.
Free Float/Slack is the amount
of time an activity can be delayed without delaying its successor (following
activity).
Lag
Time: Inserted wait time between
activities
Lead
Time: Overlapping activities, also called paralleling or fast tracking.
“Lead
In; Lag Out”
|
Three
Point Estimates, or PERT
|
Accuracy
of Estimates
|
PERT
= PROGRAM Evaluation and Review Technique
Holds
schedule and lets cost float
3
estimates for each task: Optimistic, Pessimistic, and Most Likely
Mean
Estimate = (O + 4*ML + P)/6
Standard
Deviation (s)
= (P – O)/6
Variance
= s2 ,
or [(P – O)/6]2
Standard
deviation of tasks on CP =
Sum of variances
|
Order
of Magnitude:-25% to +75%
Budget
Estimate:-10% to +25%
Definitive
Estimate:-5% to +10%
|
|
|
|
Powers
of a Project Manager
|
Conflict
Resolution (Best to Worst)
|
1.
Expert: Best, earned on your own
2.
Reward: Next best. Based on PM position
3.
Formal: Power, based on PM position
4.
Referent: Referring to positions of others
5.
Penalty: Worst. Based on PM position
|
1.Problem
Solving: Also called Confronting
2.
Compromising: Solutions satisfy both parties
3.
Withdrawal: Postponing a decision
4.
Smoothing: Emphasis on agreement
5.
Forcing: One viewpoint at expense of another.
|
|
Sources of Conflict
(Order of Priority)
|
Herzberg’s Motivators
|
1.
Schedules
2.
Project Priorities
3.
Resources
4.
Technical Opinions
5.
Administrative Procedures
6.
Cost
7.
Personality
|
1.
Achievement
2.
Recognition
3.
Challenge of the work itself
4.
Responsibility
5.
Advancement
6.
Growth
|
|
Channels of Communication
|
|
Between
Team Members = N(N-1)/2
|
Project
is closed when administrative closure is complete.
Administrative
closure is done at end of each Project Phase and at the end of the Project.
Contract
closure: verification that deliverables were acceptable; it is done once at the
end of the contract.
Contract
Closure Procedure is produced under “Close Project”
|