Login(Email) Password Forget Password? Account Settings
Home ASP.net System Info C# Books Java Script Visual C++(MFC) C/C++ Win API Java Contact Us
Key Concept and Formulas for PMP Exam
Earn Value Formulas  Project Selection Financials
PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
SV = EV – PV (minus is behind schedule)
CV = EV – AC (minus is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV)    Use when variances are atypical
EAC = AC + [(BAC-EV)/CPI]   Use when variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BAC – EAC
ETC = BAC – EV   Use when variances are atypical
ETC = (BAC – EV)/CPI   Use when variances are typical
ETC = EAC – AC    Use when original estimates were flawed
NPV (Net Present Value) = FV/(1+r)n 
FV= Future Value, r= interest rate, n= no. of time periods
Higher NPV is better
IRR (Internal Rate of Return) = Solve the NPV equation for “r”
Also called Hurdle Rate
Higher IRR percentage is better
BCR (Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is better
ROI (Return on Investment) = Earnings/Investment
Higher ROI is better
Payback Period = Time to recover cost of the project
Lower payback period is better
Cash Flow = Cash In – Cash Out
Network Diagram Calculating Stackor Float
Precedence Diagramming Method (PDM)
  • Also called Activity on Node (AON): Activities are in boxes
  • Most commonly used today
  • Has 4 relationships: F-S, S-S, F-F, S-F
  • No “dummies” (zero duration dependencies) allowed
  • Can analyze using either Three-Point Estimates or CPM
Arrow Diagramming Method (ADM)
  • Also called Activity on Arrow (AOA)
  • Only 1 relationship: F-S
  • Can have “dummies”
  • Can analyze using either Three-Point Estimates or CPM
Graphical Evaluation and Review Technique (GERT)
  • Allows loops and repetitive activities
Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date.
Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity).
  • LS – ES:    Calculates slack with forward pass
  • LF – EF:    Calculates slack with backwards pass

Lag Time:  Inserted wait time between activities

Lead Time: Overlapping activities, also called paralleling or fast tracking.

“Lead In; Lag Out”

Three Point Estimates, or PERT
 Accuracy of Estimates
PERT = PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic, Pessimistic, and Most Likely
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (s) = (P – O)/6
Variance = s2 , or [(P – O)/6]2
Standard deviation of tasks on CP =     Sum of variances
Order of Magnitude:-25% to +75%
Budget Estimate:-10% to +25%
Definitive Estimate:-5% to +10%
 Powers of a Project Manager  Conflict Resolution (Best to Worst)
1. Expert: Best, earned on your own
2. Reward: Next best. Based on PM position
3. Formal: Power, based on PM position
4. Referent: Referring to positions of others
5. Penalty: Worst. Based on PM position
1.Problem Solving: Also called Confronting
2. Compromising: Solutions satisfy both parties
3. Withdrawal: Postponing a decision
4. Smoothing: Emphasis on agreement
5. Forcing: One viewpoint at expense of another.
Sources of Conflict (Order of Priority)
Herzberg’s Motivators
1. Schedules
2. Project Priorities
3. Resources
4. Technical Opinions
5. Administrative Procedures
6. Cost
7. Personality
1. Achievement
2. Recognition
3. Challenge of the work itself
4. Responsibility
5. Advancement
6. Growth
Channels of Communication
Closing
Between Team Members = N(N-1)/2
Project is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and at the end of the Project.
Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract.
Contract Closure Procedure is produced under “Close Project”
script>