| Project
INTEGRATION Management |
| Knowledge Areas |
Major Processes desc. |
Primary Inputs |
Tools & Techniques |
Primary Outputs |
| Integration |
|
|
|
|
| Develop Project
Charter |
Developing the
project charter that formally authorizes a project or a project phase |
1. Contract (when applicable)
2. Project Statement of Work
3. Enterprise environmental factors
4. Organizational Process Assets
|
1. Project Selection Methods
2. Project Management Methodology (PMM)
3. Project Management Information system(PMIS)
4. Expert Judgment |
1. Project Chapter |
| Develop Preliminary Project Scope Statement |
Developing Preliminary Project Scope
Statement that provides high level scope narrative. |
1. Project Charter
2. Project Statement of Work
3. Enterprise Environmental Factors
4. Organizational Process Assets |
1. PMM
2. PMIS
3. Expert Judgment |
1. Preliminary project Scope Statement |
| Develop Project Management Plan |
Documenting the actions necessary to define,
prepare, integrate and coordinate all subsidiary plans into a project
management plan. |
1. Preliminary project Scope Statement
2. Project Management Processes
3. Enterprise Environmental Factors
4. Organizational Process Assets |
1. PMM
2. PMIS
3. Expert Judgment |
1. Project Management Plan |
| Direct and Manage Project Execution |
Executing the work defined in the project
management plan to achieve the project’s requirements defined in the project
scope statement. |
1. Project Management Plan
2. Approved Corrective actions
3. Approved Preventive Actions
4. Approved Change Requests
5. Approved defect repair
6. Validated defect Repair
7. Administrative Closure Procedure |
1. PMM
2. PMIS |
1. Deliverables
2. Requested Changes
3. Work Performance Information
4. Implemented corrective actions
5. Implemented Preventive actions
6. Implemented Change Requests
7. Implemented defect repair |
| Monitor and Control Project
Work |
Monitoring and Controlling the
processes used to initiate, plan, execute, and close a project to meet the
performance objectives defined in the project management plan |
1. Project Management Plan
2. Work Performance Information
3. Rejected Change Requests |
1. PMM
2. PMIS
3. Earned Value Technique
4. Expert Judgment |
1. Recommended corrective actions
2. Recommended Preventive actions
3. Recommended Defect Repair
4. Forecasts
5. Requested Changes
|
| Integrated Change Control |
Reviewing all change requests, approving
changes, and controlling changes to the deliverables and organizational process
assets. |
1. Project Management Plan
2. Deliverables
3. Work Performance Information
4. Requested Changes
5. Recommended corrective actions
6. Recommended Preventive actions
7. Recommended Defect Repair |
1. PMM
2. PMIS
3. Expert Judgment |
1.Project Management Plan(updates)
2. Project Scope Statement (updates)
3. Deliverables
4. Approved corrective actions
5. Approved corrective actions
6. Approved Change Requests
7. Rejected Change Requests
8. Approved Defect Repair
9. Validated Defect Repair |
| Close Project |
Finalizing all activities across all of the
project management process groups to formally close the project or a project
phase. |
1. Project Management Plan
2. Contract Documentation
3. Deliverables
4. Work Performance Information
5. Enterprise environmental factors
6. Organizational Process Assets
|
1. PMM
2. PMIS
3. Expert Judgment |
1. Administrative closure Procedure
2. Contract closure Procedure
3. Final Product, Service or result
4. Organizational Process Assets (updates)
|
|
|
Integration Management
|
|
Unification, Consolidation, articulation and interactive actions that are
crucial to project completion. Integration is about making choices, about where
to concentrate resources and effort. It also involves making tradeoffs among
competing objectives and alternatives. PM and team must address every process
and level of implementation for process
|
| Project Deliverables
|
| Need to be integrated with ongoing operations.
|
| Reasons to start projects |
|
1. Problems 2. Market Opportunity 3.Business Requirements
|
| Project Charter |
|
1. Authorize project
2. Gives Project Manager Authority
3.Issued by initiator or sponsor external to project organization who has the
authority to fund.
4. It is broad enough that it does not have to change as the project changes
|
| Project Charter Contain
|
|
1. Requirements that specify Customer/Sponsor Needs, wants and expectations
2.Business Needs
3.Project purpose or justification
4. Assigned PM authority 5.Stakeholder influence
6.Functional organization participation
7.Assumptions & Constraints
8.Business case and return on investment
9.Summary Budget
|
| Environmental Process Assets |
| Company Culture & Structure, Government or industry
standards, infrastructure, existing human resources, personal administration
(Hire, Fire, performance), work authorization, Market place condition, Stake
holder risk tolerance, Commercial database, PMIS
|
| Organizational
Process Assets |
| Standards, Policies, Standard
Product and Project Life Cycles, Quality policies & procedure, performance
measurement criteria, Templates, Communication requirements, Project Closure
Guidelines, Risk Control procedure, Issue and Defect Management Procedure,
Change Control Procedure, Procedure for Approving & issuing work
authorization. It also include Process Measurement database, project files,
Historical information & Lessons learned, Configuration management
database, financial database containing labor hours, costs & budgets
|
| Project
Selection Methods |
|
1.Benefit Measurement Methods (Comparative Approach)
1. Scoring Models
2. Benefit Contributions
3. Murder board – Panel of people who try to shoot down a new project idea.
4. Peer Review
5. Economic Models
1. Benefit Cost Ratio
2. Cash Flow
3.Internal Return Rate
4. Preset Value (PV) and net present value (NPV)
5.Opportunity Cost
6. Discounted Cash Flow
7. Return On Investment
2.Constrained Optimization Methods (Mathematical Models)
1. Linear 2. Nonlinear 3. Dynamic 4. Integer 5. Multiple Objective Programming
|
| Preliminary
Project Scope Statement Contain |
|
1.Project & Product Objectives
2.Requirements & Characteristics
3.Acceptance Criteria
4.Boundaries
5.Requirements and Deliverables
6.Constaints
7.Assumptions
8.Project Organization
9.Initial Defined Risks
10.Schedule Milestone
11.Initial WBS
12.Order of Magnitude Cost Estimate
13. Configuration Management Requirements
|
| Project
Management Plan |
| It defines how project is executed, monitored and
controlled and Closed. PMP can be either summary level or detailed and can be
composed of one or more subsidiary plans and other components. It contains
following management plans 1. Scope 2.Schedule 3.Cost 4.Quality 5.Risk
6.Communication 7.Procurement 8.Schedule Baseline 9.Process improvement Plan
10.Staff 11.Mile Stone list 12. Resource Calendar 13.Cost Baseline 14.Quality
Baseline 15.Risk Register
|
| Configuration
Management |
| It is a sub system of overall project management
information system. It is a means of monitoring and controlling emerging
project scope against the scope baseline; its purpose is to control change
throughout the project. It is any documented procedures used to apply technical
and administrative direction and surveillance to audit the items and system to
verify conformance requirements. . It documents the physical characteristics of
formal project documents and steps required to control changes to them (e.g.
would be used by a customer who wishes to expand the project scope after the
performance measurement baseline has been established). When more than one
individual has sign a Charter, you have to be concerned with competing needs
and requirements impacting your efforts on configuration management |
|
Configuration Management Activities |
| 1.Configuration Identification 2.Configuration Status
Accounting 3.Configuration Verification and auditing |
|
Change Control System
|
| It is a collection of formal
documented procedures that define how project deliverables and documentation
are controlled, changed and approved. It is a subsystem of configuration
management. It must also include procedures to handle changes that may be
approved without prior review (e.g. result of an emergency) |
|
Integrated Change Control
|
|
It is performed from project inception through completion, it includes
-
Identifying that a change needs to occur or has occurred
-
Make sure only approved changes are implemented
-
Reviewing and approving requested changes
-
Managing approved changes as and when they occur and regulating them
-
Maintain integrity of baseline
-
Review and approve all recommended corrective and preventive actions
-
Controlling and updating scope, cost, budget, schedule and quality
-
Documenting impact of requested changes
-
Validating defect repair
|
| Changes |
| if the functional manager wants to make a change to
time associated to a task (change in goals and objectives of the Charter) and
there is not enough reserve, senior management (not the Project Manager) should
authorize the change. The best method to control changes on the project is to
look for sources of change. The best method to deal with changes is to direct
the changes to the Change Control Board. Project Manager has authority to
approve some change requests. He is given authority to approve Changes in
Emergency Situations.
|
| Integrated change Control |
| Occurs during all the project management processes.
|
| Project Baseline |
| should be changed for all implemented changes.
Sometimes, certain classification of changes gets automatic approval on a
project and do not need Change Control Board approval.
|
| Project Plan |
| as an input to team development, the project plan
describes the technical context within which the team operates |
| Project Execution
|
| Although the products, services or results of the
project are frequently in the form of tangible deliverables such as building,
road or software, intangible deliverables such as training is also provided.
|
| Schedule Change Control System
|
| can include the paper, systems and approvals for
authorizing changes. The project manager is normally not the approval
authority, and not all the changes approved
|
| Organization Process Assets |
|
|
Includes an index & location of project documentation
-
Formal Acceptance
-
Documentation
-
Project Files
-
Closure Documents
-
Historical information
|
|
|
| Difference between Configuration
Management and Change Management systems
|
|
Both the Configuration Management and Change Management systems are sub systems
of the ICC.
They are to be understood as: Configuration Management System - Relates to
maintaining the changes to the product of the project. Change Control System -
Relates to maintaing the changes to the Project itself. Take a small example.
Your project is to design a latest design washing machine. You have 2 things
here. 1- is a Project whose objective is to design the washing machine 2- is a
Product of the project - which is the washing machine itself. All the
characteristics of the Washing Machie viz., height, capacity, drum diameter,
motor speed, color etc are called configuration of the product. This is
maintained in the Configuration Management Database. Any change to this
configuration will be managed through the Configuration Management System.(CMS)
On the other hand, there will be plans for controlling scope, cost , time and
quality in the project. Any change in these constraints would be managed
through the Change Control System (CCS). Hope this helps.
|
|
|
|